Enclosures speed up electrical installation for new pre-cast hospital build13 September 2016

Spelsberg IBT junction boxes helped speed up build Spelsberg IBT junction boxes helped speed up hospital build

Thanks in part to the use of Spelsberg IBT junction boxes, a project to build a new £89m mental health hospital in South Wales has kept to a rigorous construction programme.

The IBT enclosure range provides quick and robust electrical installations for pre-cast concrete construction, a proven method of building fast-track projects. The 20,000sq m centre replaces several separate facilities spread around Cardiff and the surrounding area. It will provide adult inpatient accommodation in 135 single-bed en-suite rooms, and also bring together all the area’s general adult mental health inpatient services including low security, addiction, neuropsychiatry, intensive care and supportive recovery services. The design incorporates sitting rooms, garden areas, therapeutic spaces and consulting rooms.

Despite being a large and complex project, topping out of the main buildings was completed within a year. This was achieved through a highly sophisticated technique to prefabricate seven separate plant rooms off-site. These were then installed in a matter of days. Each plant room contains all the building services equipment required, including pumps, fans, Building Management System (BMS) panels, control equipment and complete wiring.

The use of precast concrete panels, rather than poured concrete or other construction methods also helped ensure the rigorous building programme was maintained. The panels are bespoke designs and incorporate the electrical services, which reduced the amount of installation and wiring needed on-site.

Historically, this method of electrical installation has been difficult, due to the lack of specially designed electrical products. But Spelsberg’s ITB range of junction boxes and related products has been specifically designed for the precast construction industry.

The IBT system allows enclosures, junction boxes, lighting outlets and other installation components to be fixed into the formwork into which the liquid concrete will be poured. They are secured in place either by magnetic couplings for metal formwork, or by patented support spars for timber formwork. Conduit is fitted as required to accommodate the wiring and then the concrete is poured in. Once set, the formwork is removed and the panels are ready for shipment to site.

A key element of the IBT system is the integral sealing, which prevents concrete fines from getting inside the electrical components. This uses a patented diaphragm system which, after the conduit is inserted, returns to its original position and provides strain relief and sealing without the need for special grommets. Conventional housings do not have such a seal, so if used in a precast panel, a sealing arrangement would have to be fitted in-situ, a difficult and costly process.

The IBT products are made from halogen-free, high-temperature resistant material which is designed for a long, trouble-free life. The range available in a wide range of sizes. With more and more projects now requiring extra low voltage (ELV) transformers for LED lighting, loudspeakers and network communications cables, Spelsberg has also developed the complementary IBTronic range.

The IBT system has already been used in a wide range of buildings including prisons, schools, hotels, offices and residential buildings. It is now increasingly recognised for its potential to reduce installation time and save overall build costs.

Mark Venables

Related Companies
Spelsberg els UK Ltd

This material is protected by MA Business copyright
See Terms and Conditions.
One-off usage is permitted but bulk copying is not.
For multiple copies contact the sales team.